Challenges
- Mountainside construction with soil classification of stable rock made excavation extremely difficult
- Roughed in concrete decks for placement in sub-zero temperatures
- Coordination of nearly 1,000 RFC’s and 200 ASI’s which dramatically affected our scope of work from the contract documents
Success
- 22,209 man hours with zero OSHA restricted days or lost time accidents and received no citations from two unannounced OSHA visits
- Project completed 2 months ahead of schedule with 3,000 saved man hours
- Successfully executed nearly 1,000 RFC’s and 200 ASI’s